DAMS

 

16.35 MW ARCA HYDROELECTRIC POWER PLANT PROJECT

Project Title :Arca 16,35 MW Hydroelectric Power Plant Project
Employer :Gürsu Temiz Enerji Üretim A.Ş.
Location :Trabzon / Turkey
Completion Date :2012
Partnership :Güriş – Ecetur Joint Venture
Brief Description
:The project includes all the civil, mechanical erection and electrical installations of 16,35 MW Arca HEPP Project.Type: Hydroelectric Power StationTransmission System: Conduit type +Tunnel (5037m)Tunnel Length: 5037m( Dimension 5.7 x 5.9m)Tunneling Method: 3709 m with NATM + 1.327 m with Open Cut

Drainage Area : 734.6 Km2

Installed Power : 16,35 MW



  • ARCA 16,35 MW HYDROELECTRIC POWER PLANT PROJECT
  • ARCA 16,35 MW HYDROELECTRIC POWER PLANT PROJECT
  • ARCA 16,35 MW HYDROELECTRIC POWER PLANT PROJECT
  • ARCA 16,35 MW HYDROELECTRIC POWER PLANT PROJECT
  • ARCA 16,35 MW HYDROELECTRIC POWER PLANT PROJECT
  • arca2
  • arca1
  • arca23

4 X 175 MW ALTINKAYA DAM AND HYDROELECTRIC POWER PLANT PROJECT

Project Title:4 x 175 MW Altınkaya Dam and Hydroelectric Power Plant Project
Employer :General Directorate of State  Hydraulic Works  (DSİ)
Location :Samsun/ Turkey
Completion Date :1989
Partnership :Güriş – Yüksel Joint Venture
Brief Description :Construction of rock fill with puddle clay type dam and HEPP with a capacity of 4x 175 MW on    Kızılırmak river
ØCrest Length  : 634 m
ØCrest Width  : 15 m
ØDam Height  : 195 m
ØTotal Storage Capacity  : 16 x 106 m³
ØSpillway  : Still basin with radial gates
ØGate   : 6 nos. (13.30 m x 15.50 m)
ØFlood velocity  : 11.800 m³/sec
ØEnergy Tunnels  : 2x 9.80 m diameter twin tunnels with 274 + 350 m length.
ØPower Plant Type  : Semi-open
ØTurbine Type   : Vertical Axis, Francis
ØExcavation  : 22.000.000 m³
ØFill  : 16.000.000 m³
ØConcrete  : 550.000 m³
ØGrouting  : 20.000 m³
ØInstalled capacity  : 4x 175= 700 MW
  
  • 4X175 MW ALTINKAYA DAM AND HEPP
  • 4X175 MW ALTINKAYA DAM AND HEPP
  • 4X175 MW ALTINKAYA DAM AND HEPP
  • 4X175 MW ALTINKAYA DAM AND HEPP
  • 4X175 MW ALTINKAYA DAM AND HEPP

 

2 X 24 MW MANAVGAT DAM AND HYDROELECTRIC POWER PLANT PROJECT

Project Title:2 X 24 MW Manavgat Dam and Hydroelectric Power Plant Project
Employer :Kepez and Antalya Region Power Plants Co., Inc.
Location :Antalya / Turkey
Completion Date :1987
Brief Description :The project includes the construction of concrete dam, power house, spillway,  radial   gates, intake   structure, switch yards.
ØExcavation   : 120.000 m³
ØExcavation in Rock  : 80.000 m³
ØEmbankment   : 150.000 m³
ØConcrete  : 150.000 m³
ØFormwork (Climbing)  : 65.429 m²
ØComposed Steel Structure  : 2.545 Ton
ØDrilling  : 3.261 m
ØGrouting   : 277 ton
  
  • MANAVGAT DAM AND HYDROELECTRIC POWER PLANT
  • MANAVGAT DAM AND HYDROELECTRIC POWER PLANT
  • MANAVGAT DAM AND HYDROELECTRIC POWER PLANT
  • MANAVGAT DAM AND HYDROELECTRIC POWER PLANT

 

DIVERSION TUNNELS OF ALTINKAYA DAM

Project Title:Diversion Tunnels of Altınkaya Dam
Employer :General Directorate of State  Hydraulic Works  (DSİ)
Location :Samsun / Turkey
Completion Date :1982
Brief Description
:The project comprises the construction of two concrete coated, horse-shoe   cross-sectional diversion tunnels.Tunneling Method    :N.A.T.M.Total Length  : 735 m + 963 mTunnels Boring Diameter  : 10,40 m

Tunnel internal Diameter  : 9,00 m

Tunnel Excavation  : 192.000 m³

Open Excavation  : 1.040.000 m³

Steel shoring  : 252.000 kg

Shotcrete  : 8.800 tons

Rock bolts   : 12.000 kg

Wire mesh  : 12.000 kg

Steel pile  : 1.755 m

Curved Formwork  : 43.700 m²

Formwork  : 30.200 m²

  
  • DIVERSION TUNNELS OF ALTINKAYA DAM
  • DIVERSION TUNNELS OF ALTINKAYA DAM
  • DIVERSION TUNNELS OF ALTINKAYA DAM
  • DIVERSION TUNNELS OF ALTINKAYA DAM

 

QUICK LINKS
PROJELERİMİZ
CONTACT

ANKARA CADDESİ NO: 222
KARAOĞLAN MAHALLESİ
GÖLBAŞI 06830
ANKARA

Questions : Contact

Google Map   |   İletişim Formu

CONTACT

GURIS CONSTRUCTION ENGINEERING CO. INC.
ANKARA CADDESİ NO: 222
KARAOĞLAN MAHALLESİ
GÖLBAŞI 06830
ANKARA
TURKEY

 
© 2015 GÜRİŞ. All rights reserved.