PIPELINES AND MICROTUNNELLING

 

ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE VI

Project Title:Ankara Natural Gas Renewal and Extension Phase VI
Employer :Başkent Doğalgaz Dağıtım A.Ş.
Location :Ankara, Turkey
Completion Date :2010
Brief Description :

The project includes the engineering and the construction of the sixth phase natural gas network.

Medium pressure  PE coated steel lines:  170.014 mt

High pressure PE coated steel lines:  64.065 mt

Polyethylene  main lines (Æ 63 – 315, PE 80) :  535.176 mt

Polyethylene service lines (Æ 32 – 125, PE 80) :  246.620 mt

Service lines:  12.359 pieces

Area regulators (500 m3/h – 12.000 m3/h):  55 pieces

High pressure area regulators ( 5.000 m3/h – 75.000 m3/h)  8 pieces

  
  • ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE VI
  • ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE VI

 

ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE V

Project Title:Ankara Natural Gas Renewal and Extension Phase V
Employer :General Directorate of EGO
Location :Ankara / Turkey
Completion Date :2008
Brief Description :

The project includes the engineering and the construction of the fifth phase natural gas network.

Medium pressure  PE coated steel lines:  92.873 mt

High pressure PE coated steel lines:  25.995 mt

Polyethylene  main lines (Æ 63 – 315, PE 80) :  204.003 mt

Polyethylene service lines (Æ 32 – 125, PE 80) :  159.481 mt

Service lines:  6.873 pieces

Area regulators:  36 pieces

High pressure area regulators:  2 pieces

  
  • ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE V
  • ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE V
  • ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE V

DS 117 /2 MAIN PUMPING STATION

Project Title:DS 117 2 Main Pumping Station
Employer :Dubai Municipality
Location :Dubai / UAE
Completion Date :2007
Partnership :GURIS + ACD International Joint Venture
Brief Description :

Scope of the project comprises the construction of total 20.455 m sewage line, 24.400 m house connection line, 37192 m drainage line, 811 nos. manhole and 510 nos. gullies.

  
  • DS 117 /2 MAIN PUMPING STATION
  • DS 117 /2 MAIN PUMPING STATION
  • DS 117 /2 MAIN PUMPING STATION
  • DS 117 /2 MAIN PUMPING STATION
  • DS 117 /2 MAIN PUMPING STATION

DS 131 AL BARSHA SEWERAGE AND DRAINAGE PROJECT

Project Title:DS 131 Al Barsha Sewerage and Drainage Project
Employer :Dubai Municipality
Location :Dubai / UAE
Completion Date :2007
Partnership :GURIS + ACD International Joint Venture
Brief Description :

Scope of the project comprises the construction of total construction of 105 km uPVC, 4.5 km GRP and 8.2 km AC pipelines, 897 nose manhole, 99 nos. gullies and 2287 nos. house connection, construction of pumping station, construction of 270000 m3 retention pond.

  
  • DS 131 AL BARSHA SEWERAGE AND DRAINAGE PROJECT
  • DS 131 AL BARSHA SEWERAGE AND DRAINAGE PROJECT
  • DS 131 AL BARSHA SEWERAGE AND DRAINAGE PROJECT
  • DS 131 AL BARSHA SEWERAGE AND DRAINAGE PROJECT
  • DS 131 AL BARSHA SEWERAGE AND DRAINAGE PROJECT
  • DS 131 AL BARSHA SEWERAGE AND DRAINAGE PROJECT

 

SATU MARE SOUTHERN INDUSTRIAL PARK

Project Title:Satu Mare Southern Industrial Park
Employer :Ministry of Development and Planning
Location :Satu Mare / Romania
Completion Date :2005
Brief Description :

Construction of the infrastructure network of the industrial zone area in Satu Mare.

   

ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE IV

Project Title:Ankara Natural Gas Renewal and Extension Phase IV
Employer :General Directorate of EGO
Location :Ankara / Turkey
Completion Date :2005
Partnership :GURIS + UCAR Joint Venture
Brief Description :

The project includes the engineering and the construction of the fourth phase natural gas network.

Medium pressure steel lines:  171.807 mt

Main/service polyethylene lines:  675.617 mt

High pressure steel lines:  41.976 mt

  
  • ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE IV

 

TARSUS WASTE WATER PROJECT INFRASTRUCTURAL WORKS

Project Title:Tarsus Waste Water Project Infrastructural Works
Employer :Tarsus Municipality Water and Sewerage Operation (TASKİ)
Location :Mersin / Turkey
Completion Date :2004
Partnership :GURIS + AYMIR Joint Venture
Brief Description :

Potable Water Network    (Æ 80-355 PVC pipe)  :   38.813 mt

(Æ250-600 Ductile pipe):  14.728 mt

Waste Water Network  (Æ250-1000 HDPE pipe)   :98.220 m t

Storm Water Network  (Æ300-2200 concrete pipe)  :96.165 mt

Road paving  145.000 m2

Road paving with prefabricated concrete tiling  :278.000 m2

Sub base construction  :90.500 m3

Trench excavation  :700.000 m3

Road excavation  :133.000 m3

  
  • TARSUS WASTE WATER PROJECT INFRASTRUCTURAL WORKS
  • TARSUS WASTE WATER PROJECT INFRASTRUCTURAL WORKS
  • TARSUS WASTE WATER PROJECT INFRASTRUCTURAL WORKS
  • TARSUS WASTE WATER PROJECT INFRASTRUCTURAL WORKS
  • TARSUS WASTE WATER PROJECT INFRASTRUCTURAL WORKS

 

ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE III

Project Title:Ankara Natural Gas Renewal and Extension Phase III
Employer :General Directorate of EGO
Location :Ankara / Turkey
Completion Date :2002
Brief Description :

Medium pressure steel lines   :115.345 m

Main/Service Polyethylene Lines  :588.293 m

B-RMS Station Assembly  :27 pcs.

Number of Service Line  :8.055 pcs.

  
  • ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE III
  • ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE III
  • ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE III
  • ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE III
  • ANKARA NATURAL GAS RENEWAL AND EXTENSION PHASE III

 

BURSA ORGANIZED INDUSTRIAL ZONE NATURAL GAS MAIN DISTRIBUTION SYSTEM

Project Title:Bursa Organized Industrial Zone Natural Gas Main Distribution System
Employer :Bursa Chamber of Commerce & Industry Directorate of Organized Industry Area
Location :Bursa / Turkey
Completion Date :1992
Brief Description :

Within the scope of Natural Gas Main Distribution System of Bursa Organized Industrial Zone, followings works have been accomplished:

ØLaying of steel pipeline in various diameters of total length of 9.230 meters
ØLaying of PE pipeline in various diameters of total length of 13.528 meters
ØValve assembly
ØCathodic protection and radiographic test of steel pipeline
ØErection of metering stations
ØErection of pressure reducing stations
ØVarious civil and steel construction works
ØSupply and installation of SCADA System
   

İZMİR SEWERAGE SYSTEM PART 2

Project Title:İzmir Sewerage System Part 2
Employer :Bank of Provinces
Location :İzmir / Turkey
Completion Date :1990
Brief Description :

The project comprises the construction of the tunnel and collector with a total length of 3983 meter by using New Austrian Method.

  
  • İZMİR SEWERAGE SYSTEM PART 2
  • İZMİR SEWERAGE SYSTEM PART 2

 

INTRASTRUCTURAL WORKS OF ANTALYA FREE ZONE

Project Title:Infrastructural Works  of Antalya Free Zone
Employer :General Directorate of DLH
Location :Antalya / Turkey
Completion Date :1988
Brief Description :

Within the scope of the project following works have been accomplished:

ØSite preparation works
ØRoad and paving concrete works
ØConstruction of administration building of an area of 1.340 m²
ØLaying of concrete sewerage pipes of various diameters totally 6.200 m long
ØLaying 11.000 mt. A.C.P. pipes of various diameters.
ØWater tank construction with the capacity of 1.500 m³
  
  • INTRASTRUCTURAL WORKS OF ANTALYA FREE ZONE
  • INTRASTRUCTURAL WORKS OF ANTALYA FREE ZONE

 

QUICK LINKS
PROJELERİMİZ
CONTACT

ANKARA CADDESİ NO: 222
KARAOĞLAN MAHALLESİ
GÖLBAŞI 06830
ANKARA

Questions : Contact

Google Map   |   İletişim Formu

CONTACT

GURIS CONSTRUCTION ENGINEERING CO. INC.
ANKARA CADDESİ NO: 222
KARAOĞLAN MAHALLESİ
GÖLBAŞI 06830
ANKARA
TURKEY

 
© 2015 GÜRİŞ. All rights reserved.