HISTORY OF GURIS

2017- 200 MW DINAR RES: THE SECOND LARGEST WIND POWER PLANT OF TURKEY

 
  • 200 MW DINAR WPP, the second largest wind power plant of Turkey, has been completed and is in operation. DINAR WPP will generate
    564.000.000 kws electricity annually and this will supply the electricity need of 235.000 household. Commissioning of the plant has been completed by using SIEMENS SWT 2,3-108 and GE 2,75-120 turbine technology.   
  • GURIS has completed purchasing of 5.4  MW SEYIT ONBASI WPP owned by Aksa / Kazancı Holding and added the plant into its portfolio. SEYIT ONBASI WPP located in Ayvacik - Canakkale has an installed capacity of 9.4 MW.
      
  • GURIS has completed the purchasing procedure of 18 MW ATIK WPP owned by Aksa / Kazancı Holding and added the plant into its portfolio. ATIK WPP located in Belen - Hatay has an installed capacity of 30 MW.    
  • GURIS has purchased the license of 88 MW KOCATEPE WPP.
  • The acceptance of 22.6 MW EFE 6 of our EFELER GEOTHERMAL POWER PLANT has been completed and the plant is in commercial operation. 
  • GURIS has purchased the license of 120 MW YUVACIK WPP.

 

2016 - Our Energy Investments...

  • The acceptance of  80 MW FATMA (Mugla) WPP which exists in the investment, construction and operation programme of DERNE CLEAN ENERGY GENERATION CO. INC. of which GURIS is % 100 shareholder, is completed and the electricity generation has started. 80 MW FATMA WPP will generate approximately 211.500.000 kwh electricity annually. 
  • The acceptance of 25.6 MW ZELIHA (Uskup / Kırklareli) WPP which exists in the investment, construction and operation programme of DERNE CLEAN ENERGY GENERATION CO. INC. of which GURIS is % 100 shareholder, is completed and the electricity generation has started. 25.6 MW ZELIHA WPP will generate approximately 92.000.000 kwh electricity annually. 
     
  • GÜRİŞ has purchased 25.78 MW CERMIKLER HYDROELECTRIC POWER PLANT. Cermikler HEPP, located in Sıvas city, has an installed capacity of 25.78 MW and is generating 80.651.000 kWh of electricity annually. In other words Cermikler HEPP meets the needs of monthly electricity of 27.000 houses. With this new investment, the number of hydroelectric power plants that Güriş owns becomes six and the total installed capacity of hydroelectric power plant investments rises to 104.38 MW.
     
  • GURIS has purchased 14.07 MW ESPIYE HEPP. Espiye HEPP, located in Giresun city, has an installed capacity of 14.07 MW and is generating 57.500.000 kWh of electricity annually. In other words Espiye HEPP meets the needs of monthly electricity of 20.000 houses. With this new investment, the number of hydroelectric power plants that GURIS owns becomes five and the total installed capacity of hydroelectric power plant investments rises to 78,6 MW.

2015 - Our Energy Investments ...

  • The partial acceptance of 64 MW KANIJE (UZUNKOY/EDIRNE, HAYRABOLU/TEKIRDAG) WPP which exists in the investment, construction and operation programme of DERNE CLEAN ENERGY GENERATION CO. INC. of which GURIS is % 100 shareholder, is completed and the electricity generation has started. 
  • The acceptance of 47.4 MW EFE 1 of our EFELER GEOTHERMAL POWER PLANT has been completed and the plant is in commercial operation. 
  • The acceptance of 22.5 MW EFE 4 GEOTHERMAL POWER PLANT, the fourth unit of the largest geothermal power plant in TURKEY with an installed capacity of 232.3 MW, has been realized and electricity generation is started. 
  • The acceptance of 22,5 MW EFE 3 GEOTHERMAL POWER PLANT, the third unit of the largest geothermal power plant in TURKEY with an installed capacity of 232.3 MW, has been realized and electricity generation is started.
  • The name of the owner of SARIKAVAK HEPP changed from COMERTOGLU ENERGY INVESTMENTS CO. INC. to KACKAR ELECTRIC GENERATION CO. INC.
  • GÜRİŞ has purchased Arpa Hydroelectrical Power Plant having an installed capacity of 32.9 MW, located on Arpa Creek of Borçka County of Artvin City. The license duration of Arpa HEPP is 49 years. Company name changed as POKUT ELECTRIC GENERATION CO. INC.
  • GÜRİŞ has purchased % 100 shares of MCK ELECTRICITY GENERATION CO.INC., the company WHO has the license of ARPA HEPP.
  • GÜRİŞ has incorporated TAHTA HYDROELECTRIC POWER PLANT found on Tahta Creek of Kadirli province located within the boundaries of Osmaniye and Kahramanmaraş to its investments. TAHTA HEPP of which the installed capacity is 12.3 MW is generating approximately 53.400.000 kwh electricity annually and the duration of the generation license is 49 years. Company name changed as TRIPOLI ELECTRIC GENERATION CO. INC.  
  • GÜRİŞ has purchased % 100 shares of TAHTA ELECTRIC GENERATION CO. INC. 

2014 - 22.5 MW EFE 2 plant has been realızed and electrıcıty generatıon has started.

  • The provisional acceptance of 22.5 MW EFE 2 plant, second unit of Turkey's largest geothermal power plant with an installed capacity of 232.2 MW, has been realized and electricity generation has started.    

2013 - Our Energy Investments...

  •  GURIS has purchased Sarıkavak HEPP located on Kurtsuyu Creek, bayou of Goksu River and with this purchase the total installed capacity has reached to 262 MW. Sarıkaya HEPP with an installed capacity of 8.89 MW is generating 42.000.000 kwh electricity annually.

  •  GURIS has purchased 100% share of WEST CRIMEA WES LIMITED LIABILITY COMPANY, a company existing under the Ukrainian law. West Crimea WES has the concession rights to develop, construct, and electricity generation for West Crimea Wind Power Plant in Chornomorske Region located in the northwestern part of the Autonomous Republic of Crimea, and the company has also signed grid connection agreement. The Project will have total installed capacity of 250 MW, and is planned to be constructed in two stages of 125 MW, with 1st phase planned to be put into operation before the end of 2014. 

  • GURIS has purchased 100% share of GIMAK ENERGY GENERATION CO. LTD. with this purchase GURIS becomes the owner of 8.2 MW Çeşmebaşı Hydroelectric Power Plant on Kızılırmak river. Çeşmebaşı HEPP is the first HEPP owned by GURIS and the plant generates annually 56.160.000 kwhour electricity on average.
  • GURIS CONSTRUCTION AND ENGINEERING CO. INC., has purchased 100% shares of IBERDROLA RENEWABLE ENERGY GENERATION, TRADE AND INDUSTRY LTD. CO. in Turkey, the affiliate company of Spanish IBERDROLA RENOVABLES ENERGIA S.A.U. Company name changed as DERNE CLEAN ENERGY GENERATION CO. INC.

    With this purchase, GURIS became the license owner of;

    48 MW Kanije WPP in Edirne
    15 MW Zeliha WPP in Kırklareli
    70 MW Fatma WPP in Muğla.
    Investments are planned to be commenced in 2013. 
  • Shares of BURC GEOTHERMAL INVESTMENT ELECTRIC GENERATION CO. INC. have been purchased by GURIS GROUP COMPANIES. EFE GEOTHERMAL POWER PLANT, which is an investment of BURC GEOTHERMAL INVESTMENT ELECTRIC GENERATION CO. INC., planned to be constructed at Aydin Province, Germencik and İncirliova Countries, Omerbeyli Village. Electricity generation licence provided by EMRA on 13.12.2012 with the reference number EU/4165-16/2491 for an installed capacity of 162.5 MW. Regarding to the approval of EMRA, shares of BURC GEOTHERMAL INVESTMENT ELECTRIC GENERATION CO. INC. have been purchased by MOGAN ENERGY INVESTMENT HOLDING CO. INC., GURIS HOLDING CO. INC., GURIS CONSTRUCTION AND ENGINEERING CO. INC. and GURENERGY ELECTRIC GENERATION LIMITED CO. which are GURIS GROUP COMPANIES. 

2012 – 55th anniversary of GURIS was celebrated.

  • 55th anniversary of GURIS was celebrated.
  • GURIS has purchased % 50 share of WEST CRIMEA WES LLC which has the right to develop the project, construct the plant and generate the electricity of West Crimea Wind Power Plant with an installed capacity of 250 MW in THE AUTONOMOUS REPUBLIC OF CRIMEA.
  • SANTRAL MINING CO. INC. has been founded in 2012 for the purpose of exploring, extracting and processing underground sources. With its own technology and logistics, the company, through its investments, aims to reach efficiency, growth and sustainability for the acquisition of metal and industrial minerals in Turkey and worldwide.

2011 – OLGU ENERGY INVESTMENT GENERATION AND TRADE CO. INC.

  • GURIS has purchased 100% shares of OLGU ENERGY INVESTMENT GENERATION AND TRADE CO. INC., the owner the license of 50 MW Wind Power Plant in Afyon Dinar.

2010 – EOLOS WIND ENERGY GENERATION CO. INC.

  • Wind power plant licence was obtained for Antakya-Senkoy from Energy Market Regulatory Authority (EMRA).
  • Investing company of Senkoy wind power plant called EOLOS WIND (renewable) ENERGY GENERATION CO.INC. was established.
  • Yarubiye / Syria Clinker milling plant came into operation.

2009 – Commercial production and electric selling started in Germencik / Aydın GPP.

  • Commercial production and electric selling started in Germencik / Aydin geothermal power plant. (47.4 MWe largest geothermal power plant in Turkey)
  • Raqqa / Syria Clinker milling plant, invested and installed by GURIS Group came into operation.
  • Belen RES 30 MWe (3 MWe x 10 Turbine) has started to produce electricity.

2008 – In the Shareholder’s extraordinary meeting held on 29.08.2008 of Guris Construction…

  • In the Shareholder’s extraordinary meeting held on 29.08.2008 of GURIS CONSTRUCTION & ENGINEERING CO. INC., the capital of the Company was increased from 100.000.000.-TL to 390.000.000.-TL
  • Within the boundaries of Province of Hatay, in district of Belen, the construction of BELEN WIND POWER PLANT of which annual production amount foreseen would be 96.000.000 kWh /year with a total power of 30 MW was commenced.

2007 – 50th anniversary of GURIS was celebrated.

  • 50th anniversary of GURIS was celebrated.
  • A branch was inaugurated in Tripoli / Libya and the first contract was signed.

2006 – GURIS RAQQA CEMENT CO. INC.

  • GURIS RAQQA CEMENT CO. INC. was founded in the city of Raqqa in Syria.
  • A branch was inaugurated in Jeddah of Saudi Arabia.
  • The Construction Contract of Jeddah City Center and Southern Region 2nd Stage Main And Ancillary Sewerage Networks was signed as GURIS + Al Mabani (Lebonan) + Dallah (Saudi Arabia) Joint Venture.
  • Environmentally friendly Guris has initiated the construction of Aydin Germencik Geo-Thermal Power Plant./Aydin.

2005 – GURIS DUBAI LLC

  • GURIS DUBAI LLC Company was founded in Dubai and the first contract in Dubai was signed.

2004 - GURMAT ELECTRIC POWER GENERATION CO. INC. was founded…

  • GURMAT ELECTRIC POWER GENERATION CO. INC. was founded.
  • A new school was added to our donations to Turkish Public Education Ministry: Yamanturk Multi Program High School started education. /Armutlu-İZMİR

2003 - GURENERJI ELECTRIC POWER PRODUCTION CO. INC. was founded…

  • GURENERJI ELECTRIC POWER PRODUCTION CO. INC. was founded.
  • In Bucharest / Romania, GURIS ROMANIA S.R.L company was founded and first contract in Romania was signed.

2002 - BELEN ELECTRIC GENERATION CO. INC. was founded…

  • BELEN ELECTRIC GENERATION CO. INC. was founded.
  • In the Shareholder’s extraordinary meeting held on 20.12.2002 of GURIS HOLDING CO., the capital of the Company was increased from 16.000 TL to 15.000.000 TL.

2001 – ISO 9001 Certificate was issued…

  • ISO 9001 Certificate was issued.
  • Construction of Ankara Metro 3rd Phase Batikent – Sincan Linewas commenced. / Ankara
  • Yamanturk Primary School which is one of the schools donated to Turkish Public Education Ministry started education. /Cayeli-Rize

2000 – ASIL STEEL INDUSTRY AND TRADE CO. INC. …

  • ASIL STEEL INDUSTRY AND TRADE CO. INC. was purchased by GURIS + YAZICI Group from the Turkish Privatization Administration.
  • The Construction of Natural Gas Renewal and Expansion Projects/ Ankara
  • The Contract for Bursa Ring Road Yalova Exit – Turankoy Flyover function Section was signed as GOCAY – GURIS Joint Venture. / Bursa
  • Turkan Yamanturk Primary School which was donated to Turkish Public Education Ministry started education. /ANKARA

1998 – The Bursa Light Rail System 1st Phase Construction Contract was signed…

  • The Bursa Light Rail System 1st Phase Construction Contract was signed by the GURIS + Siemens Aktiengesellschaft + Simko + Tuvasas Consortium. / Bursa
  • Yamanturk High School which was donated to Turkish Public Education Ministry started education./ANKARA
  • The first road project after many years was signed: Contract for Giresun – Espiye Motorway Section of the Black Sea Highway, by GURIS – METIS Joint Venture.

1996 – MIRAJ TOURISM AND TRADE CO. INC. was founded…

  • MIRAJ TOURISM AND TRADE CO. INC. was founded and construction of its own hotel investment Miraj Park Resort Hotelcommenced. / Antalya
  • TOPRAK MARBLE INDUSTRY CO. INC. was founded. (GURIS CONSTRUCTION & ENGINEERING CO. + Nurol Holding Corp + Milangaz LPG Distribution Corp. (Demiroren Group) + Toprak Paper Industry Corp. as the founding partners)
  • OMTAS AUTOMATIVE TRANSMISSION ASSEMBLY INDUSTRY & TRADE CO. INC. has joined the Group.

1995 – Contract for the realization of Izmit Urban and Industrial water supply project …

  • Contract for the realization of Izmit Urban and Industrial water supply project that was the biggest water supply project financed by the private sector as the first build – operate – transfer model application of Turkey was signed by Thames Water (England), Gama Industry, GURIS Construction, Mitsui & Co.Ltd. (Japan) and Sumitomo Co. Inc. (Japan)
  • Yamanturk High School which was donated to Turkish Public Education Ministry started education. / MALATYA

1994 – Two Buildings which have been constructed…

  • Two Buildings which have been constructed (National Reassurance – Istanbul and Park Place Business Center and Residences – Moscow) won the architectural design awards of the same year in two different countries.
  • The construction of the 3 x 210 MW Yatagan Thermal Power Plant Flue Gas Desulphurization Facility was commenced GURIS + Gottfried + Bischoff ( Germany) Consortium.

1993 – Construction and Erection of Cayirhan Thermal Power Plant Units III & VI

  • Contract for Construction and Erection of Cayirhan Thermal Power Plant Units III & VI was signed as and by GURIS + AE & E (Austuria) + Bischoff (Germany) + Siemens + Mitsubishi (Japan) + Caillard – Lavache (France) Consortium.

1992 – The construction contract of Ankara Metro 1st Stage Kizilay – Batikent Line…

  • The construction contract of Ankara Metro 1st Stage Kızılay – Batıkent Line that was the first Metro Project of Turkey, was signed as and by the Ankara Metro Consortium (GURIS CONSTRUCTION AND ENGINEERING CO. INC. + GAMA INDUSTRY PLANTS CONSTRUCTION AND INSTALLATION CORP + SNC LAVALIN INC. and BOMBARDIER INC.)

1990 – The construction of Inonu University Research and Application Hospital…

  • The construction of Inonu University Research and Application Hospital, which is a research and application hospital was commenced. / Malatya

1989 – MERKEZ INSURANCE CO. INC. was founded…

  • MERKEZ INSURANCE CO. INC. was founded.

1987 – Joined to the MIR CONTRACTING AND TRADE CO. INC. as the founding partner…

  • Joined to the MIR CONTRACTING AND TRADE CO. INC. as the founding partner.
  • The Moscow Office was opened in RUSSIA.

1983 – GURIS EXPORT, IMPORT AND MARKETING CO. INC. was founded…

  • GURIS EXPORT, IMPORT AND MARKETING CO. INC. was founded.
  • Contract for Construction of Petlas Tire Factory was signed. / Kirsehir

1982 – Baghdad Office was established in IRAQ….

  • Baghdad Office was established in IRAQ.
  • The first overseas business was undertaken in Iraq: The contract was signed for Extension Works of Falluja White Cement Factory, Units III & IV.

1981 – The first office abroad started its activities in Duesseldorf. / GERMANY…

  • The first office abroad started its activities in Duesseldorf. / GERMANY

1980 – The Contract between DSI (State Hydraulic Works) and GURSEL JV…

  • The Contract between DSI (State Hydraulic Works) and GURSEL JV for the construction of the Altinkaya Dam (4x175MWe) which is one of the largest dams of Turkey with HEP Plants in Samsun was signed under the leadership of Guris.

1979 – Altinkaya Dam, Construction of Diversion Tunnels / Samsun…

  • Altınkaya Dam, Construction of Diversion Tunnels / Samsun
  • PARSAT MACHINERY INDUSTRY AND MARKETING CO.INC. was founded.

1977 – Cayirhan Thermal Power Plant, Construction and Erection of Units I & II / Ankara…

  • Cayırhan Thermal Power Plant, Construction and Erection of Units I & II / Ankara

1976 – Fabrication and Erection of 23 Harbor Cranes / Hopa – Antalya – Derince – Bandirma…

  • Fabrication and Erection of 23 Harbor Cranes / Hopa – Antalya – Derince – Bandırma
  • As the beginning of environmental projects: Construction of Ankara Water Treatment Plants, Sections I and II (GURIS + Water Project International Ltd. (England) Partnership). / Ankara

1975 – GURIS MACHINERY AND ERECTION INDUSTRY INC. was founded…

  • GURIS MACHINERY AND ERECTION INDUSTRY INC. was founded.
  • GURIS HOLDING was founded.
  • ELSA ELECTRONIC INDUSTRY AND TRADE INC. joined the Group.

1974 – The first harbor work: Construction of Iron & Steel Factories Harbor / Iskenderun…

  • The first harbor work: Construction of Iron & Steel Factories Harbor / İskenderun
  • Thermal Power Plant and getting acquainted with a foreign partner for the first time: GURIS + Vereiniote Kessel Werke (Germany) Ordinary Partnership signed the contract of Seyitomer Thermal Power Plant, Construction of Unit III. /Kutahya.

1973 – GURIS CONSTRUCTION AND ENGINEERING CO. INC.

  • GURIS limited company transformed into GURIS CONSTRUCTION AND ENGINEERING CO. INC.

1968 – Was a turning point…

  • Was a turning point. Dalaman Cellulose and Paper Factory Construction/ Mugla was the first business requiring fairly detailed design and the first project with a foreign consultant.
  • PARSAN MACHINERY PARTS INDUSTRY CO.INC. was founded.

1965 – Fatsa Port Construction Project /Ordu…

  • Fatsa Port Construction Project /Ordu

1963 – Yemisen Stream Rehabilitation Project /Golbasi-Adiyaman…

  • Yemisen Stream Rehabilitation Project /Golbasi-Adiyaman
  • Bentderesi Rehabilitation Project / Ankara

1959 – Cubuk Creek Rehabilitation Project /Ankara…

  • Cubuk Creek Rehabilitation Project /Ankara
  • Kazova Irrigation Left Bank Construction Project /Tokat

1958 – GURIS was founded as a limited company….

  • GURIS was founded as a limited company.
  • Signed the first Contract: Kırıkkale Elmadag Power Transmission Line / Ankara
QUICK LINKS
PROJELERİMİZ
CONTACT

ANKARA CADDESİ NO: 222
KARAOĞLAN MAHALLESİ
GÖLBAŞI 06830
ANKARA

Questions : Contact

Google Map   |   İletişim Formu

CONTACT

GURIS CONSTRUCTION ENGINEERING CO. INC.
ANKARA CADDESİ NO: 222
KARAOĞLAN MAHALLESİ
GÖLBAŞI 06830
ANKARA
TURKEY

 
© 2015 GÜRİŞ. All rights reserved.