The scope of the project comprises the following;
ØOpen – Close Tunnel, underground and above ground stations, line works, water, sewerage, telecom, electric, natural gas NATO pipeline infrastructure displacement works,
ØConstruction, installation and steel construction works of the transmission and maintenance center (OMC Building with 10,000 m² indoor area) which is required for the system,
ØConstruction works between the route and operation and maintenance center and within the operation maintenance center area,
ØConstruction and installation works of 17 above ground and underground stations planned along the route,
ØConstruction works of transformer / Rectifier centers which will meet the energy requirement of Phase I,
ØConstruction works related to the energy feeding lines, overhead systems, posts of the whole route.